PROJECT RESUMED MONDAY, APRIL 10, 2023!
Potholing and Utility Exploration at
Channel Bridges in Huntington Beach
PERIODIC LANE CLOSURES REQUIRED
PROJECT SUMMARY
OC Public Works…
Project Progress
75% Complete!
As of March 2023, 780-feet of channel has been completed — that’s 75% of the total project! Other items we’ve checked off our punch-list in Zone 3 near Woodland…
PROJECT SUMMARY
The Santa Ana Gardens Channel Bikeway Extension Project will improve safety for bicyclists and pedestrians and will provide connections to the existing and future bikeways. It is…
PROJECT SUMMARYOC Public Works will complete repairs and maintenance at Capistrano Beach Park, an OC Parks beach, within the City of Dana Point. Public access may be limited during construction.…
PROJECT SUMMARY
OC Public Works will complete temporary repairs to Carbon Creek (B01) Flood Control Channel within unincorporated County right-of-way and adjacent to the City of Anaheim.…
NOTICE OF PROJECT COMPLETION
EAST GARDEN GROVE-WINTERSBURG
CHANNEL IMPROVEMENT PROJECT
O C T O B E R 2 0 2 0 — M A R C H 2 0 2 3
Watch our before and after video footage at:…
Join this meeting online via Zoom:
Link will be posted here when available.
Meeting ID: TBD
Passcode: TBD
NOTICE OF PUBLIC MEETING
Santiago Creek Flood Risk Management
Update on Proposed…
Modjeska Grade Road
Assessments for Future Improvements Project, Will Require Lane Closures Over Two-Day Period
WHAT
In preparation of a future project, OC Public Works will be assessing…