Project Update Laguna Canyon Channel Replacement Project March 2023

Current Project ProgressWork Completed to DateAs of February, 675 feet of channel replacement has been completed, as well as the drainage structures and the reinforced concrete bridge at Woodland…

Construction Alert Carbon Creek Channel April 1028 2023

PROJECT SUMMARY OC Public Works will complete temporary repairs to Carbon Creek (B01) Flood Control Channel within unincorporated County right-of-way and adjacent to the City of Anaheim.…

Construction Alert Kempton Storm Channel Rehabilitation Project

OC Public Works will complete a rehabilitation project in the unincorporated Orange County area of Rossmoor. Construction begins upstream of the San Gabriel River at the 605 Freeway and continues 1,…

Maintenance Alert Talbert Channel Ocean Outlet Aug24 22 Nov 23 22

WHAT Crews will use large equipment to remove accumulated excess sand from the Talbert Channel outlet in Huntington Beach, as allowed through a regulatory permit.  This…

Construction Alert Fairview Channel Maintenance Project in City of Costa Mesa Sept 26 Dec 26 2022

NOTE: PARTIAL LANE CLOSURE ALONG PLACENTIA AVE. PROJECT SUMMARY OC Public Works will complete a channel maintenance project at the Fairview Channel in the City of Costa Mesa. The project…

Construction Alert Yorba Linda Islands Road Improvements Nov 7 Late Dec 2022

CONSTRUCTION ALERT: Yorba Linda Islands Road Improvements TEMPORARY ROAD CLOSURES REQUIRED WHEN November 7 — Late December 2022 Working Days/Times: Mon. — Fri., 7 a.m. — 4 p.m…

Project Update Laguna Canyon Channel Replacement Project

PROJECT UPDATE JANUARY 2023 LAGUNA CANYON CHANNEL REPLACEMENT PROJECT Woodland Drive to the southern end of Laguna Canyon Frontage Road Current Progress — 43% Complete! Work…

Construction Alert Installation of Traffic Monitoring Equipment Lane Closures Needed Aug 23 22 Feb 2023

Starting August 23, 2022, OC Public Works contractors will be installing new fiber optic cable and equipment along Crown Valley Parkway and a section of O’Neill Drive in Ladera Ranch. Temporary lane…

Construction Alert Antonio Parkway Daisy Street Road Grinding and Resurfacing AugSept 2022

OCPW will begin two "grind and overlay" projects along Antonio Parkway on  August 1, 2022. Location specific construction notifications can be downloaded at the bottom of this post/page.…

Project Update East Garden GroveWintersburg Channel

CURRENT STATSConstruction is 70% complete with an anticipated completion date of December 2022.20,000 linear feet of sheet piles installed! That’s 100% complete!7,000 linear feet improved…